Engineer: Rock County bridges are OK

By
Sara Quam

Although Rock County has some structurally deficient bridges and functionally obsolete bridges, a tragic collapse isn’t imminent.
County Engineer Mark Sehr shared bridge information with the County Board of Commissioners Tuesday.
He said he’s had a lot of questions since the Minneapolis Highway 35W bridge fell into the river during rush hour, killing 13 people.
The governor has requested thorough county inspection of bridges, and Rock County is in the process of that.
“We don’t have any glaring issues with what I’ve seen so far,” Sehr said.
If greater problems are found, Sehr said he’ll further evaluate and post weight limits or close a bridge to traffic.
Rock County has 22 bridges that are structurally deficient and functionally obsolete; townships have 22; the city of Beaver Creek has one and the city of Luverne has two.
The county is responsible for all bridges in the county that aren’t state or federal.
The Rock River bridge on the east end of Luverne will be replaced next year.
Sehr said, “We’re on track for that in June. We have $1 million federal funding for that.”
Since 1996, the Rock County Highway Department has replaced 98 bridges.
Many of the county’s bridges aren’t even that noticeable when driven over, but any structure more than 10 feet long is considered a bridge.
Some that appear to be old timber bridges were actually updated with steel pilings, so looks can be deceiving.
Sehr said that if people have specific questions on bridges, his office can help. The ratings are all accessible and the bridges have been inspected on a rotating schedule even before the governor’s order.
Bridges have ratings on a scale of 1 to 9 (9 is best) based on scores from different parts of the bridge.
Structurally deficient bridges have ratings of 4 or lower on the roadway, beams, trusses, or substructures.
Functionally obsolete bridges have a rating of 3 or lower on the width or “under clearance.”
Structural sufficiency is used to determine eligibility for federal funding. It is based on structural condition, bridge geometry and traffic considerations.
Scores are from 0 (very poor) to 100 (excellent). A bridge with a sufficiency rating of 80 or lower is eligible for federal rehabilitation funds. A bridge with a rating less than 50 is eligible for federal replacement.
Local bridge inspectors must be certified by the Minnesota Department of Transportation. All the information is forwarded to the Federal Highway Administration.
Fixing feedlots
Commissioners approved a process for the remaining few livestock producers not willing to correct pollution problems.
Through a complete feedlot inventory the county has uncovered problems with some producers, most of whom have changed for the better or are in the process of changing.
Those who refuse to comply will go through the following steps with the county:
1. The county will send a letter explaining the problem with the feedlot and that this will be the last year to take advantage of using the old feedlot evaluation model to make corrections.
2. The county will follow up with a phone call or personal visit.
3. The county will review the problem with the Soil and Water Board and the county commissioner of the producer’s district.
4. The county will send a certified letter to the producer offering a meeting with the Soil and Water Board Chairman and the appropriate Soil and Water Supervisor and commissioner.
5. The county attorney will become involved and send a Notice of Violation.
6. The case will be turned over to the Minnesota Pollution Control Agency.

You must log in to continue reading. Log in or subscribe today.