Work continues on Highway 75

Lead Summary

Six blocks of Highway 75 in Luverne remain closed between Main Street and Dodge Street for a sewer lining project that started Oct. 17 and was expected to last one month. The infrastructure work includes sewer lining, spot repairs, installing new manholes and replacing water service lines beneath the highway by direction boring new service lines. Hulstein Excavation of Edgerton was awarded the contract in February after submitting the low bid of $567,000, including alternates. The city is using the federal funding in the American Rescue Plan to pay for the project.