The Rock River Bridge will be replaced after all, just later than expected.
County Engineer Mark Sehr told Rock County Commissioners Tuesday that the bridge will be replaced starting in February 2009, and ending by Labor Day 2009.
The original plan for the $2.39 million project scheduled replacement of the bridge for this summer, but a steel shortage caused the delay.
Contractor Duininck Brothers cannot get steel until January.
Sehr said, “The price is good, it’s just that we can’t get the steel beams.”
When the bids and timetables came to the board from contractors two weeks ago, the county wasn’t sure how it would handle the project, which was planned to be completed this summer.
Sehr said the bridge will be open on one lane throughout the project in order to allow local residents and emergency services to cross the river as needed.
Otherwise, crossing the river would put people miles out of their way.
At the most, the bridge will be closed for 72 hours at a time a few times during the project.
The bridge has been ranked as one of the five worst for sufficiency ratings in the state.
It has a daily traffic count of about 3,000, which is a high number for this county.
Most of the funding for the bridge project will come from federal and state money.
The steel costs make up $539,172 of the project.