A construction crane is set up near the Rock River bridge on East Main Street to begin the long-awaited bridge replacement project.
The first step in the $2.39 million project is to construct a temporary pedestrian bridge, and workers are driving in pilings for that part of the project this week.
The total replacement project is estimated to last nearly a year, but one lane of traffic will be open over the river for the majority of the work.
At the most, the bridge will be closed for 72 hours at a time for a few times during the project.
The Rock River bridge in Luverne, built in 1931, is ranked one of the five worst in the state with a sufficiency rating of 6.8 on a scale of 100 — 100 being the best.
The ranking covers only bridges 100 feet or longer with traffic counts of more than 100 per day.
The Rock River bridge is 248 feet long and has an average daily traffic count of about 3,000, which is high for Rock County’s population.
There are three other bridges in the state, in Dakota, Clay and Ramsey County, that have worse ratings than the Rock River bridge in Luverne.
Most of the funding for the local bridge project will come from federal and state money.
Federal funding will comprise $1 million of the project’s cost, in addition to $888,430 from the Minnesota bridge bond fund and $498,187 from County State Aid funds.
The federal funding is possible because of the bridge’s poor ranking.
A bridge with a sufficiency rating of 80 or lower is eligible for federal rehabilitation funds. A bridge with a rating less than 50 is eligible for federal replacement.
The Rock River bridge has cracks in both directions of the deck.
The beams also qualify as poor, with cracking and exposed and rusted steel reinforcements, which were added over the years to extend the life of the bridge.
The steel costs make up $539,172 of the project.
Work was originally scheduled to begin this summer, but a steel shortage forced a delay, with steel beams available in January.
Erickson Engineering, Bloomington, designed the new bridge, with the circular rail detail similar to the 1930s design of the original bridge.
The prime contractor is Duininck Brothers, Inc., Prinsburg.
Call the Rock County Highway Engineer, Mark Sehr, at 283-5010 with questions.
Overall, Rock County has 21 bridges that are structurally deficient and functionally obsolete — townships have 21; the city of Beaver Creek has one and the city of Luverne has two.
Most are very small, but structures longer than 10 feet are considered bridges.
Since 1996, the Rock County Highway Department has replaced 101 bridges.
The county is responsible for all bridges that aren’t state or federal.
Bridge replacement project getting started
Subhead
Temporary pedestrian bridge being built; one lane open for most of construction
By
Lori Ehde