Airport runway work starts Monday

By
Lori Ehde

Work on Luverne’s airport runway expansion is set to begin Monday, and the Luverne Township road, 91st Street, will close within a couple of weeks after that work begins.
City Council members took action Tuesday to secure state and federal funding for the project with a resolution authorizing the execution of a grant agreement to fund Phase 1 of the work.
The agreement is between the State of Minnesota and the City of Luverne that includes land acquisition and grading work for the new 4,200-foot runway.
These two parts of the project — Phase 1 — will cost $1,326,016, which is broken down so the federal portion is $736,435, state is $490,574, and Luverne will pay $99,007.
The total five-year capital improvement plan for the airport considers more than $3 million in improvements.
In 2009 the new runway will be paved (with FAA funding) at $1,194,000.
A new hangar in 2012 is still an estimate at this point, but it’s proposed that the city will need extra stalls once the runway is completed to required standards and will be able to accommodate twin engine airplanes.
City Councilman Pat Baustian, who serves on the Airport Board, said three aircrafts have already reserved hangars, knowing that the new runway will be longer. “So, we’ll need more aircraft hangar space,” Baustian said.
If the funding blend between local, state and federal funding remains the same, the local balance of that $3 million total amount will be $319,650.